Installation of screening equipment

Customer: Estonian Cell AS

Task: Installation of additional screening equipment in the AS Estonian Cell aspen wood pulp plant along with the construction of the required piping and structures. The capability for purification of processing water was improved.

Completed: 2014

Construction of the circulation water pipes of Estonian Cell

Customer: Estonian Cell AS

Task: Construction of the water pipe circulation system at Estonian Cell using directional drilling. Two hundred fifty-two (252) m of water piping (diameter 160 mm) was installed into sandstone on the plant’s premises.

Completed: 2014

Extension of the waste water treatment system at Estonian Cell

Customer: Estonian Cell AS

Task: In the course of the design and construction of the waste-water treatment system extension, a new waste-water pre-processing structure was built with an underground pumping station and a distribution chamber, as well as an anaerobic treatment process for biogas production. In the course of the construction work, the plumbing and power lines needed for the station’s operation were also built. Biogas pressure lines to the plant were installed in order to enable the plant to use the gas it produced. Construction works on the ventilation equipment, power and weak current lines of the technical building and the installations were also carried out.

Completed: 2013